Introduction
Nebius, the AI infrastructure provider known as a neocloud company, is signaling aggressive growth with a plan to spend as much as $45 billion by 2027. The figure emerged during its third-quarter earnings call and far exceeded analyst expectations. The company intends to fund much of that buildout not with its own balance sheet alone, but through customer prepayments and loans secured by future contracts. That approach has worked so far, but new setbacks at a key customer site are putting the strategy under pressure.
What Happened
Nebius disclosed a $40 billion capital expenditure plan for 2027, with total spending potentially reaching $45 billion. The company reported third-quarter revenue of $981 million, marking a 571% increase compared with the same period last year, though about one-third of that sum came from a single partnership-related payment. It also reduced its 2026 revenue projection by $200 million, setting it at $3 billion, and pointed to holdups at third-party locations including the New Jersey site. The stock fell 17% following the announcement.
The most visible problem is in Vineland, New Jersey, where a data center operated by DataOne is significantly delayed. Nebius has a contract with Microsoft worth up to $19.4 billion for AI computing capacity at that site. Originally, portions of that capacity were supposed to arrive in 2025 and 2026. Now, slightly more than half is slated for delivery by year's end, while the rest has been moved to the second quarter of 2027.
Nebius attributes the delay to DataOne's decision to shut down temporary power generation sooner than anticipated while the site transitions to Bloom Energy fuel cells. The transition has not been smooth. New Jersey regulators fined DataOne $1.1 million after finding at least 45 unpermitted natural gas generators at the facility, and nearby residents have filed a lawsuit over noise from the site.
Microsoft, Nebius's largest customer, has the right to end affected services after a grace period if deadlines are missed and no substitute capacity is provided. Nebius says Microsoft has been involved in planning discussions, but it has not confirmed whether Microsoft accepts the revised timeline. Microsoft has not publicly canceled the agreement.
Why This Matters
Nebius's financing model depends heavily on getting projects online on time. The company expects customer prepayments and asset-backed loans to cover as much as 85% of its planned 2027 spending. If third-party sites stall, Nebius could face rising costs without matching revenue, a scenario its chief executive acknowledged during the earnings call.
Broader industry trends add to the uncertainty. Microsoft appears to be pulling back from neocloud arrangements that miss deadlines. Reports indicate the software giant is scrutinizing third-party operators including Nebius, IREN, and Nscale, and has already stepped back from some Nscale projects. Because Microsoft is both a major customer and a bellwether for enterprise AI spending, its caution could ripple across the sector.
Still, Nebius pushes back on the idea that its entire program is at risk. It says data centers it builds directly are arriving on schedule or early, and that new third-quarter contracts included prepayments exceeding construction costs. The company ended the quarter with $7.4 billion in cash and projects 2027 revenue in the range of $12 billion to $13 billion, with pre-tax breakeven expected during the final three months of the year.
Key Takeaways
- Nebius plans up to $45 billion in AI infrastructure spending by 2027, funded largely by prepayments and contract-backed loans.
- A Microsoft-backed data center in Vineland, New Jersey, is significantly delayed, pushing some capacity to Q2 2027.
- The site operator, DataOne, faces regulatory fines and a resident lawsuit over unpermitted generators and noise.
- Microsoft can terminate services if deadlines are missed, though it has not publicly canceled its Nebius contract.
- Nebius expects prepayments and financing to cover up to 85% of its 2027 capital spending and sees pre-tax breakeven by late 2027.
Conclusion
Nebius is wagering that its prepaid, contract-backed model can support one of the largest AI infrastructure buildouts in the cloud sector. The company has cash on hand and a pipeline of customer commitments, but its biggest test may be outside its direct control. Until third-party sites like the New Jersey facility come online, Nebius's $40 billion vision remains dependent on partners, regulators, and a major customer that is showing signs of caution.